Global Furniture Brand DEDON Adopts COREnergy’s Sunshine Plan

DEDON Manufacturing becomes COREnergy’s first Sunshine Plan customer through a two-year retail electricity supply agreement.

Distressed Denim Meets Brocade In Marques’Almeida’s Spring/Summer 2027

Marques’Almeida brings rawness and refinement into the same frame for Spring/Summer 2027, pairing sculptural proportions with the brand’s instinctively undone approach.

Pre-Order And Own The Latest iPhone 18 Pro And iPhone 18 Pro Max For As Low As PHP137 Per Day With Home Credit

Home Credit Philippines gives Filipinos more flexible ways to pre-order and own the latest iPhone 18 Pro models.

Miguel Vieira: Spring-Summer 2027 Womenswear Collection “Back To Black”

Black becomes a language of its own as the Spring/Summer 2027 collection brings sculptural flowers, precise tailoring, and fluid silhouettes into focus.

DPWH To Turn Bacolod Evacuation Center Into Isolation Facility

DPWH allots a budget that will be used to redesign a regional evacuation center to an isolation facility for COVID-19 patients with mild or asymptomatic symptoms.

DPWH To Turn Bacolod Evacuation Center Into Isolation Facility

136
136

How do you feel about this story?

Express Your Reaction
Like
Love
Haha
Wow
Sad
Angry

The Department of Public Works and Highways (DPWH) has allotted PHP4 million to repurpose the regional evacuation center (REC) here into a 45-cubicle isolation facility for asymptomatic and mild coronavirus disease (Covid-19) patients.

As of Wednesday, the project is part of the 109-bed healthcare facilities identified by the DPWH for construction in Bacolod.

In a statement, Mayor Evelio Leonardia said he has agreed with the agency to proceed with the project, and the city government will facilitate the provisions for water and power supply to the facility.

“The DPWH will fund the repurposing works since the evacuation center has not yet been officially turned over to the city,” he added.

Leonardia said he pointed out to DPWH-Western Visayas regional director Lea Delfinado that a roofed walk has to be built to connect the evacuation center to the comfort room outside the building.

The city government plans to build more comfort rooms since these amenities were not built into the center’s design, he added.

The PHP33.7-million evacuation center in Barangay Vista Alegre has a two-storey main building, which can accommodate at least 300 evacuees needing temporary shelter in times of calamity or disaster.

Inaugurated in February, the facility stands on a 3,000-square meter property in the Progreso Village relocation site owned by the city government.

Aside from the accommodation building, it also has an office and infirmary building, laundry/drying area, toilet and bath for both male and female, pump room, generator room, and materials recovery facility.

In Bacolod, the DPWH Task Force to Facilitate Augmentation of National and Local Health Facilities is also building a 32-bed isolation facility in Barangay Alijis and a 32-bed off-site dormitory inside the Corazon Locsin Montelibano Memorial Regional Hospital compound. (PNA)