What Did The Foundation Actually Accomplish?

As questions swirl over UP CMC Foundation funds, stakeholders seek an accounting not just of money but of impact.

NephroPlus Philippines Strengthens Nationwide Presence With 50 Clinics

NephroPlus Philippines has expanded its nationwide network to 50 dialysis clinics, strengthening access to kidney care services across the country.

STI College Recognizes New Roster Of Distinguished Alumni Awardees For 2026

The development highlights the success stories of alumni who continue to make a difference in society through their work and service.

Delinquent At The SEC: How Did It Happen?

Regulatory questions add a new layer to the growing controversy surrounding the UP CMC Foundation.

PH’s 1st Airport Underground Railway To Unlock Growth In C. Luzon

The Philippine North Railway project inside the Freeport will unlock economic growth and the employment potentials of Central Luzon especially Bulacan and Pampanga, under the “Build, Build, Build” project, Transportation Secretary Arthur Tugade said on Saturday.

PH’s 1st Airport Underground Railway To Unlock Growth In C. Luzon

219
219

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Philippine North Railway (PNR) project inside this Freeport, which will feature the country’s first-ever airport railway express service, will unlock economic growth and the employment potentials of Central Luzon, especially Bulacan and Pampanga, under the “Build, Build, Build” project, Transportation Secretary Arthur Tugade said on Saturday.

Tugade, who inspected the excavation of the airport underground railway in front of the new terminal building of the Clark International Airport (CRK), said the project would generate direct and indirect employment opportunities for locals, overseas Filipino workers (OFWs), and transport workers affected by the coronavirus disease 2019 (Covid-19) pandemic.

“Sa katunayan, mahigit 7,000 direct jobs ang nabuksan sa construction phase ng PNR Clark Phase 2, at inaasahang 3,000 job opportunities pa ang magbubukas oras na maging operational ito. Samantala, inaasahang higit 25,000 direct job opportunities ang hatid ng buong North-South Commuter Railway (NSCR) line during construction, at 10,000 jobs naman ang maidadagdag oras na mabuksan na ito (In fact, more than 7,000 direct jobs have been opened in the construction phase of PNR Clark Phase 2, and it is expected that 3,000 job opportunities will open when it becomes operational. Meanwhile, more than 25,000 direct jobs are expected to open during the construction of the entire NSCR line, and 10,000 jobs will be added by the time it opens),” Tugade said in an official social media account post.

Joining Tugade during the inspection were provincial government officials and representatives of the Japan International Cooperation Agency and Asian Development Bank.

The underground train station of the PNR inside Clark is part of the 53-km. PNR Clark Phase 2 (Malolos-Clark segment) project.

Tugade said once operational, PNR Clark 2 will cut travel time from Malolos, Bulacan to Clark, Pampanga from 1.5 hours to 2 hours to just 30 minutes to 35 minutes.

It has six stations – Calumpit, Apalit, San Fernando, Angeles, Clark, and CRK.

This project is part of the massive 147-km. NSCR, which will have 35 stations, and shall operate 464 train cars, with 58 eight-car train sets configuration.

As of July 2021, PNR Clark Phase 2 recorded an overall progress rate of 32 percent, while PNR Clark Phase 1 (Tutuban to Malolos segment), is now 48-percent complete. (PNA)