The New Era Of Preventive Medicine: Advancing BHRT And Pharmacy Compounding Awareness In The Philippines

The growing focus on preventive medicine highlights how personalized care is reshaping the future of healthcare in the Philippines.

TESDA, Nestlé Philippines Join Forces To Empower Coffee Farmers Through Skills Development

Technical Education and Skills Development Authority and Nestlé Philippines strengthen their partnership to support coffee farmers through skills development and sustainable livelihood programs.

The BE Group Secures COREnergy Partnership To Energize Mabuhay Towers

The BE Group of Companies partners with COREnergy to improve energy management across Mabuhay Towers in Cebu.

Teachers Have Already Cut Their Workload By Up To 85% Using AI. So Why Can’t Schools Sustain It?

Teachers in the Philippines are quietly using AI to cut lesson planning time, but without system support, those gains struggle to last across schools.
X

Raslag Corporation’s Third Solar Plant Goes Online, Revenues And Earnings Underway

After getting clearance from the National Grid Corporation of the Philippines, Raslag's third venture plant went online this July.

Raslag Corporation’s Third Solar Plant Goes Online, Revenues And Earnings Underway

60
60

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

Raslag’s third venture plant went online this July after receiving approval from the National Grid Corporation of the Philippines (NGCP). Raslag’s 18.011MWp plant energization earmarks the additional revenues for the Company of about P215 million for the first two years of its operation. Offering its generation to WESM as a merchant plant, Raslag will capitalize on the uptrend of WESM prices thus far to push its financial figures higher than expected.

The 18.011MWp plant of Raslag – the largest plant in operation, doubles the Company’s solar generating capacity to 41.198 MWp. Raslag-1 (10.046MWp) and Raslag-2 (13.141MWp) both enjoy a FIT rate of P9.68/kWh and P8.69/kWh, respectively. Said FIT rates have an annual escalation based on inflation and foreign exchange rates and guaranteed for 20 years from commercial operations.

For the rest of 2022, the power plant is expected to generate 13.5 gigawatt-hours (GWh) and 27.0 GWh in 2023. It can potentially contribute revenues of around Php 71.6 million in 2022 and Php 142. 9 million in 2023, assuming an average Wholesale Electricity Spot Market (WESM) Settlement Price of Php 5.30/kWh.

The 35.159 MWp RASLAG-4, which will be the company’s largest plant once completed, is in the advanced stages of land acquisition, permitting, and development work. It is expected to achieve commercial operations status in March 2024.

With this added generation capacity, Raslag participates and supports the call from the national government to increase the renewable share of 35% in the generation mix and to reduce harmful gas emissions by 75% in 2030.