Sustainability As Reputation Infrastructure

Regulations in the Philippines now mandate structured sustainability disclosures, reinforcing the shift from voluntary initiatives to audited institutional requirements.

How Chef Tatung Learned To Let Simpol Grow Beyond Him

Behind Simpol’s familiar tone is a deliberate process, where discipline and shared understanding help transform simple content into something that resonates across platforms and audiences.

Prifood, COREnergy Team Up To Optimize Energy Use Under RAP

Prifood partners with COREnergy to optimize energy use and strengthen operational efficiency across its facilities.

9Lives And Vision Express Introduce A New Eyewear Collection With A Modern 90s Edge

The new 9Lives eyewear collection with Vision Express revisits 90s fashion through bold frames and modern design, blending nostalgia with a refined and contemporary edge.

NLEX’s Viaduct SB Lane To Undergo Repair Starting Aug. 13

Heads up, riders! There might be a possible delay once the NLEX undergoes upgrading works starting August 13.

NLEX’s Viaduct SB Lane To Undergo Repair Starting Aug. 13

36
36

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The southbound lane of Candaba Viaduct of the North Luzon Expressway (NLEX) will undergo upgrading works starting on August 13 to enhance its safety and address the long-term serviceability of the structure.

The NLEX Corporation, in its advisory on Monday, advised motorists of possible travel delays as four bridge link slabs will be replaced in phases.

Each link slab will be repaired for approximately 26 days.

To keep the lane open, a Bailey bridge will be installed over the link slab that is under repair.

The first phase of the installation of the Bailey bridge is from August 13-15.

Once installed, this will allow cars, small trucks, and buses to pass through. Big trucks will be directed to use the northbound counterflow lane.

However, 12-wheeler dump trucks will be restricted at the Candaba Viaduct southbound lane since they are found to be overweight. These will be temporarily rerouted but may re-enter NLEX southbound lane via Pulilan, Sta. Rita or Tabang in Bulacan.

The upgrading works of the Candaba Viaduct southbound are expected to be completed by December this year. (PNA)