Empowering Communities: The Climate Resilience Toolkit For Heat Health Risks

With peak temperatures approaching, Filipino communities face critical heat-related health risks that demand immediate attention and action.

Mr. Big Pillow Supports Sleep Health In The Philippines On World Sleep Day

Mr. Big Pillow hosted a significant event on World Sleep Day, bringing together lifestyle influencers in SM Makati.

BISELCO Awards 15-Year Power Supply Deal To CIPC To Strengthen Palawan’s Energy Security

BISELCO has awarded a 15-year power supply deal to CIPC, aimed at enhancing Palawan’s energy security.

Vivant Hits Record PHP2.3 Billion Core Net Income In 2024 Amid Strong Growth

Vivant Corporation reports a remarkable 20% increase in consolidated core net income for 2024, reaching Php 2.3 billion.

NLEX’s Viaduct SB Lane To Undergo Repair Starting Aug. 13

Heads up, riders! There might be a possible delay once the NLEX undergoes upgrading works starting August 13.

NLEX’s Viaduct SB Lane To Undergo Repair Starting Aug. 13

30
30

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The southbound lane of Candaba Viaduct of the North Luzon Expressway (NLEX) will undergo upgrading works starting on August 13 to enhance its safety and address the long-term serviceability of the structure.

The NLEX Corporation, in its advisory on Monday, advised motorists of possible travel delays as four bridge link slabs will be replaced in phases.

Each link slab will be repaired for approximately 26 days.

To keep the lane open, a Bailey bridge will be installed over the link slab that is under repair.

The first phase of the installation of the Bailey bridge is from August 13-15.

Once installed, this will allow cars, small trucks, and buses to pass through. Big trucks will be directed to use the northbound counterflow lane.

However, 12-wheeler dump trucks will be restricted at the Candaba Viaduct southbound lane since they are found to be overweight. These will be temporarily rerouted but may re-enter NLEX southbound lane via Pulilan, Sta. Rita or Tabang in Bulacan.

The upgrading works of the Candaba Viaduct southbound are expected to be completed by December this year. (PNA)