Women In Fintech: How Tala’s Shivani Siroya Is Changing The Future Of Credit To Advance Financial Inclusion

Women leaders continue to reshape industries by bringing new ideas and perspectives that challenge long-standing systems. Their innovations are creating solutions that impact communities worldwide.

Nestlé Philippines Honored With Special Citation, Partners Leadership Award For Advancing EPR Systems

Sustainability initiatives are encouraging both businesses and communities to participate in improving waste recovery systems.

Vivant Water Acquires Majority Stake In Puerto Princesa Wastewater Facility

Vivant Water strengthens its role in wastewater management with a larger stake in Puerto Princesa’s treatment facility, supporting long-term environmental solutions and sustainable urban development.

Unilever Philippines Boosts Local Production Capabilities Manufacturing In Cebu

Unilever Philippines strengthens local manufacturing with a new Home Care production facility in Cebu serving the Visayas and Mindanao markets.

DPWH Opens Tabang Bridge In Bulacan

The newly-reconstructed Tabang Bridge which directly connects the North Luzon Expressway to Manila North Road and the Cagayan Valley Road was formally opened to the public on Tuesday.

DPWH Opens Tabang Bridge In Bulacan

129
129

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The newly-reconstructed Tabang Bridge which directly connects the North Luzon Expressway to Manila North Road and the Cagayan Valley Road was formally opened to the public on Tuesday.

The Department of Public Works and Highways (DPWH) Bulacan 1st District Engineering Office said motorists will no longer have to endure heavy traffic and dilapidated alternative road routes as the reconstruction of the 40-year-old bridge is finished amid some unavoidable delays.

Henry Alcantara, district engineer of the DPWH-Bulacan 1st DEO during an interview, said the delay in the opening of the bridge was due to the heavy rains caused by typhoon Fabian which struck the country in July.

“The initial scheduled completion was supposed to be Aug. 15, but due to the continuous heavy rains, the activities were suspended and we’re forced to halt the operation. Isa pang nakaapekto sa proyekto ay ang suspension ng trabaho dahil (One of the factors that affected the project is the suspension of work because) of the global pandemic, particularly during the height of the enhanced community quarantine (ECQ),” Alcantara said.

He added that another cause of delay was the ongoing North-South Railway project under the Tabang Bridge as well as the changes made in design due to footing obstruction and waterline utilities.

Erning Dauz, chief of the DPWH Maintenance Division, said the reconstruction of the bridge started in January this year with a total cost of PHP31 million. The 25-meter long and 18-meter wide bridge now has four lanes.

“Eto po bubuksan na natin itong Tabang Bridge. Sa abalang nagawa, ako na po ang humihingi ng paumanhin. Isang malapad at bagong tulay para sa mga Bulakenyo (Here, we are going to open the Tabang Bridge. I apologize for the delay. A wide and new bridge for the Bulakenyos),” Alcantara said. (PNA)