A Celebration With Purpose: VCM’s 25th Anniversary Shines Through Outreach And Compassion

VCM The Celebrity Source marks 25 years by celebrating connection with purpose, choosing to give back through an outreach that highlights how legacy is built not just through success but through service.

The Toughest Phone HONOR X9d 5G Launched At PHP 17,999 With A Chance To Win Tesla Cybertruck

HONOR Philippines launches the highly anticipated HONOR X9d 5G, priced at PHP 17,999.

Why Tarantadong Kalbo Needs Only A Few Lines To Say Everything

In a crowded digital space, Tarantadong Kalbo shows how restraint and intention can make visual commentary speak louder than excess. #PAGEONESpotlight #PAGEONESpotlight_KevinEricRaymundo #PAGEONESpotlight_TarantadongKalbo

Vivant Energy Secures 15-Year PSA To Meet Siquijor’s Growing Power Demand

Vivant Energy secured a 15-year power supply agreement to support Siquijor’s growing electricity demand amid rising tourism and economic activity.

DOTr Begins Inspection Of Brand-New PNR Clark Trains

The Department of Transportation has begun the inspection of trains purchased for the Philippine National Railways Clark Phase 1 project in Valenzuela City on Wednesday.

DOTr Begins Inspection Of Brand-New PNR Clark Trains

21
21

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Department of Transportation (DOTr) has begun the inspection of trains purchased for the Philippine National Railways (PNR) Clark Phase 1 project in Valenzuela City on Wednesday.

In a Facebook post, DOTr Secretary Arthur Tugade led the inspection of the trains purchased from the Japan Transport Engineering Company and Sumitomo Corporation as part of the North-South Commuter Railway (NSCR) system.

“Fifty-eight train sets ang inaasahang tatakbo sa kabuuang NSCR mula sa Clark International Airport (CRK) hanggang sa Calamba, Laguna (58 train sets are expected to operate in the entire NSCR from the CRK to Calamba, Laguna),” Tugade said.

Despite failed attempts to build such a rail system since 1994, with the latest resulting in a protracted legal battle in an international arbitration between Northrail and SINOMACH in 2016, Tugade said the PNR Clark Phase 1 (38-kilometers long from Tutuban to Malolos) and Phase 2 (53-km long from Malolos to Clark) are now “in full swing construction.”

In addition, he said the delivery of the NSCR’s 58 eight-car train sets, or a total of 464 train cars, has started after the first train set was delivered in November 2021.

“Oras na matapos ang PNR Clark Phase 1, magiging 35 minutes na lamang ang travel time mula Tutuban, Manila patungong Malolos, Bulacan, mula sa current 1.5 hours (Once PNR Clark Phase 1 is complete, travel from Tutuban, Manila to Malolos, Bulacan will be reduced to 35 minutes from the current 1.5 hours),” Tugade said.

Both PNR Clark Phase 1 and 2 are funded through assistance from the Japan International Cooperation Agency (JICA) and the Asian Development Bank (ADB).

On the other hand, all nine civil works contracts for the construction of PNR Calamba—56-km long from Manila to Calamba—are expected to be awarded within the first quarter of 2022.

To date, the PNR Clark 1 has a 53.85 percent overall progress rate, the PNR Clark 2 at 34.46 percent, and PNR Calamba at 28.62 percent complete. (PNA)