The New Math Of Fuel Value: Why Smart Drivers Look Beyond Pump Price

Caltex puts engine cleanliness, fuel quality, and dependable performance at the center of its approach to helping drivers maximize every refill.

What’s In Store At Noel Bazaar 2026: A Modern Paskong Pinoy Experience

Noel Bazaar 2026 brings together holiday shopping, Filipino Christmas traditions, live performances, and family activities across two venues.

From Access To Agency: How Tala’s Philippine Experience Is Shaping Its ASEAN Vision

Tala is using nearly a decade of experience in the Philippines to shape its broader vision for responsible credit access across ASEAN.

Nestlé Group CEO Underscores The Strategic Importance Of The Philippines To The Company’s Growth

Nestlé Group CEO Philipp Navratil highlights the Philippines as one of the company’s most important growth markets worldwide.

Cebu’s 3rd Bridge Now 87% Complete

The online registration for the installation of radio-frequency identification stickers has now started to pass Cebu’s third bridge.

Cebu’s 3rd Bridge Now 87% Complete

248
248

How do you feel about this story?

Express Your Reaction
Like
Love
Haha
Wow
Sad
Angry

The Cebu-Cordova Link Expressway Corp. (CCLEC) has started the online registration for the installation of RFID (radio-frequency identification) stickers, which motorists will need to pass Cebu’s third bridge that is set to be operational early next year.

The company announced on Tuesday that the construction progress of the 8.9-kilometer Cebu-Cordova Link Expressway (CCLEX) project was 87.14-percent complete as of end-October.

The PHP30-billion toll bridge project, which will be substantially completed by yearend, will use an all-electronic toll collection system when it opens in the first quarter of 2022 to provide motorists with safe and seamless travel.

Motorists may register for RFID through https://mptc.outsystemsenterprise.com/ORRAS/.

Topping the construction accomplishment is the completion of the CCLEX main bridge deck that connects Cebu City and the municipality of Cordova. Works have now moved to the construction of the deck’s safety barrier.

“Earlier, we have also finished the installation of all 56 stay cables holding the main bridge deck as well as the installation of all 434 NU (Nebraska University) girders required for the entire stretch of the project. Also completed is the 200-meter pedestrian footbridge. Work on the other segments of the CCLEX project continues to progress,” CCLEC said in a statement.

At the Cebu South Coastal Road (CSCR) on ramp and off ramp sections of CCLEX, ongoing now is the construction of the deck slab following the completion of its substructure and installation of precast planks.

At the Cebu viaduct, the construction of the deck slab is also ongoing. The Cordova viaduct, on the other hand, is now structurally complete and works are now on the construction of the safety barriers.

Aside from these, works are ongoing for the toll plaza, CCLEX Operations and Maintenance Center, and the Toll Operations Center building.

CCLEX is a project of CCLEC, in partnership with the local government units of Cebu City and Cordova.

CCLEC is a wholly-owned subsidiary of Metro Pacific Tollways Corp., the toll road arm of Metro Pacific Investments Corp. (PNA)