AXE Shows A Sweeter Side To Guys With Its Two New Scents

AXE is making waves with two new scents that embrace a sweeter version of masculinity.

Celebrate Her Strength And Style With The Barbie™ And G-SHOCK Collaboration

Celebrate the unstoppable spirit of mothers with the stylish Barbie™ x G-SHOCK collaboration.

Timeless Gifts For Mother’s Day: Watches That Celebrate Every Moment With Mom

This Mother’s Day, a timeless watch encapsulates the beauty of your relationship and the moments that matter most.

At Azadore, Now Two, Chef Tatung Sarthou Rekindles The Spirit Of Filipino Gatherings

At Azadore, Chef Tatung Sarthou is celebrating two years of bringing the essence of Filipino gatherings to life, all while nestled in a charming 1960s home. #PAGEONESpotlight #PAGEONExAzadore #PAGEONExChefTatung

Cebu’s 3rd Bridge Now 87% Complete

The online registration for the installation of radio-frequency identification stickers has now started to pass Cebu’s third bridge.

Cebu’s 3rd Bridge Now 87% Complete

37
37

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Cebu-Cordova Link Expressway Corp. (CCLEC) has started the online registration for the installation of RFID (radio-frequency identification) stickers, which motorists will need to pass Cebu’s third bridge that is set to be operational early next year.

The company announced on Tuesday that the construction progress of the 8.9-kilometer Cebu-Cordova Link Expressway (CCLEX) project was 87.14-percent complete as of end-October.

The PHP30-billion toll bridge project, which will be substantially completed by yearend, will use an all-electronic toll collection system when it opens in the first quarter of 2022 to provide motorists with safe and seamless travel.

Motorists may register for RFID through https://mptc.outsystemsenterprise.com/ORRAS/.

Topping the construction accomplishment is the completion of the CCLEX main bridge deck that connects Cebu City and the municipality of Cordova. Works have now moved to the construction of the deck’s safety barrier.

“Earlier, we have also finished the installation of all 56 stay cables holding the main bridge deck as well as the installation of all 434 NU (Nebraska University) girders required for the entire stretch of the project. Also completed is the 200-meter pedestrian footbridge. Work on the other segments of the CCLEX project continues to progress,” CCLEC said in a statement.

At the Cebu South Coastal Road (CSCR) on ramp and off ramp sections of CCLEX, ongoing now is the construction of the deck slab following the completion of its substructure and installation of precast planks.

At the Cebu viaduct, the construction of the deck slab is also ongoing. The Cordova viaduct, on the other hand, is now structurally complete and works are now on the construction of the safety barriers.

Aside from these, works are ongoing for the toll plaza, CCLEX Operations and Maintenance Center, and the Toll Operations Center building.

CCLEX is a project of CCLEC, in partnership with the local government units of Cebu City and Cordova.

CCLEC is a wholly-owned subsidiary of Metro Pacific Tollways Corp., the toll road arm of Metro Pacific Investments Corp. (PNA)