When In Manila And The Long Game Of Building A Lasting Brand

A platform built on consistency now faces reinvention, as When In Manila shifts from founder-led identity to a shared space shaped by its growing community.

Unilever Champions Women Within The Workplace And Beyond Through Purposeful Programs And Partnerships

Unilever Philippines highlights how intentional policies and programs can empower women to lead, grow, and thrive across workplaces and communities.

Vivant Posts Double Digit Growth In 2025, Core Net Income Surges 21% To Php 2.7 Billion On Solid Power Generation Results

Vivant Corporation posts strong earnings growth, reflecting steady performance across its energy and water businesses amid shifting industry dynamics.

Reaching The Philippines’ Last Mile: Private Sector Innovation To Bridge The Financial Inclusion Gap

Private sector innovation is stepping in to bridge the gap between access and actual financial inclusion in underserved communities.

Butuan Airport Rehab Raises Passenger Capacity By 150%

Two government agencies led the opening of the newly-expanded terminal building in Butuan airport which is set to accommodate thrice its previous passenger capacity.

Butuan Airport Rehab Raises Passenger Capacity By 150%

129
129

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The newly-expanded terminal building at this city’s airport opened Wednesday in a ceremony joined by top officials of the Department of Transportation (DOTr) and the Civil Aviation Authority of the Philippines (CAAP).

The PHP24.5 million project covers the rehabilitation and expansion of the pre-departure area, the terminal area, and the passenger terminal building of the airport.

“Airports contribute to the development of a region, as they serve as the magnet for economic activities,” DOTr Undersecretary Roberto Lim said.

CAAP Director General Manuel Antonio Tamayo said the rehabilitation of Butuan Airport aims to further improve the connectivity of the Caraga Region to other areas in Mindanao and the rest of the country.

The expanded passenger terminal building is expected to result in a 150 percent increase in terms of passenger capacity, or from 248 to 616 passengers at any given time.

The rehabilitation also increased the terminal area by 40 percent from 1,440 square meters to 2,016 square meters.

The airport project began on Dec. 6, 2021 and was completed on Dec. 18, 2022. (PNA)