PAGEONE Group Employees Sharpen Expertise In SEO, Data Privacy, And Social Media

PAGEONE Group is taking professional development to the next level by empowering its employees with specialized workshops in SEO, data privacy, and social media marketing.

Get Ready For A Game Changing Premium Running Experience In The QC Eco-Run This November

Runners, prepare yourselves for a premium experience at the QC Eco Run. Join the movement to preserve nature while enjoying a 10k, 5k, or 2k run in Quezon City.

PHINMA Properties Expands Its Range Of Developments Across The Country

PHINMA Properties believes in dignified housing solutions for every Filipino, enhancing lives through quality design.

Food Fortification Day: Nestlé PH Urges Action On Child Micronutrient Deficiencies

Today we honor National Food Fortification Day, emphasizing the importance of combating micronutrient deficiencies in children. Nestlé Philippines stands committed to making a difference.

Butuan Airport Rehab Raises Passenger Capacity By 150%

78

Butuan Airport Rehab Raises Passenger Capacity By 150%

78

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The newly-expanded terminal building at this city’s airport opened Wednesday in a ceremony joined by top officials of the Department of Transportation (DOTr) and the Civil Aviation Authority of the Philippines (CAAP).

The PHP24.5 million project covers the rehabilitation and expansion of the pre-departure area, the terminal area, and the passenger terminal building of the airport.

“Airports contribute to the development of a region, as they serve as the magnet for economic activities,” DOTr Undersecretary Roberto Lim said.

CAAP Director General Manuel Antonio Tamayo said the rehabilitation of Butuan Airport aims to further improve the connectivity of the Caraga Region to other areas in Mindanao and the rest of the country.

The expanded passenger terminal building is expected to result in a 150 percent increase in terms of passenger capacity, or from 248 to 616 passengers at any given time.

The rehabilitation also increased the terminal area by 40 percent from 1,440 square meters to 2,016 square meters.

The airport project began on Dec. 6, 2021 and was completed on Dec. 18, 2022. (PNA)