The New Math Of Fuel Value: Why Smart Drivers Look Beyond Pump Price

Caltex puts engine cleanliness, fuel quality, and dependable performance at the center of its approach to helping drivers maximize every refill.

What’s In Store At Noel Bazaar 2026: A Modern Paskong Pinoy Experience

Noel Bazaar 2026 brings together holiday shopping, Filipino Christmas traditions, live performances, and family activities across two venues.

From Access To Agency: How Tala’s Philippine Experience Is Shaping Its ASEAN Vision

Tala is using nearly a decade of experience in the Philippines to shape its broader vision for responsible credit access across ASEAN.

Nestlé Group CEO Underscores The Strategic Importance Of The Philippines To The Company’s Growth

Nestlé Group CEO Philipp Navratil highlights the Philippines as one of the company’s most important growth markets worldwide.

Bridge Connecting Binondo, Intramuros 88% Complete

The Binondo-Intramuros Bridge is now 88.63% complete!

Bridge Connecting Binondo, Intramuros 88% Complete

58
58

How do you feel about this story?

Express Your Reaction
Like
Love
Haha
Wow
Sad
Angry

The Binondo-Intramuros Bridge is nearing completion, with the overall progress now at 88.63 percent, the Department of Public Works and Highways (DPWH) reported in a news release on Friday.

Undersecretary Emil Sadain reported to DPWH acting Secretary Roger Mercado that with the completed basket-handle tied steel arch main bridge over Pasig River, the target finish is by the first half of 2022.

The bridge was originally planned to open to motorists by the end of 2021 but the DPWH had to push back the timeframe to relocate public and private services and utilities in the area, as well as to wait for the pre-fabricated steel materials from China, which financed the PHP3.39 billion project.

Work suspensions due to the pandemic restrictions also affected the progress.

Sadain said the installation of pre-fabricated girders for abutments and ramps has begun while already lifted on piers are steel box girder components for the up-ramp at the Intramuros side with a total length of 191 meters and between Piers 5 and 8 for the viaduct structure over Estero de Binondo and corresponding ramp at the Binondo side.

“We are expecting a lot of dramatic changes for this project, with all the needed materials and high-performance launching equipment available on the construction site,” he said in a statement.

Considered one of the flagship infrastructure projects of the DPWH under the “Build, Build, Build” program, the bridge project is expected to not only cut travel time between the two busy districts of Intramuros and Binondo in Manila but also benefit about 30,000 vehicles daily.

The 680 linear-meter bridge will connect the historic district of Intramuros at Solana Street and Riverside Drive with bustling Binondo at Rentas Street/Plaza del Conde Street and Muelle dela Industria Street. (PNA)