Global Furniture Brand DEDON Adopts COREnergy’s Sunshine Plan

DEDON Manufacturing becomes COREnergy’s first Sunshine Plan customer through a two-year retail electricity supply agreement.

Distressed Denim Meets Brocade In Marques’Almeida’s Spring/Summer 2027

Marques’Almeida brings rawness and refinement into the same frame for Spring/Summer 2027, pairing sculptural proportions with the brand’s instinctively undone approach.

Pre-Order And Own The Latest iPhone 18 Pro And iPhone 18 Pro Max For As Low As PHP137 Per Day With Home Credit

Home Credit Philippines gives Filipinos more flexible ways to pre-order and own the latest iPhone 18 Pro models.

Miguel Vieira: Spring-Summer 2027 Womenswear Collection “Back To Black”

Black becomes a language of its own as the Spring/Summer 2027 collection brings sculptural flowers, precise tailoring, and fluid silhouettes into focus.

Berong Nickel Exceeds Mine Rehab Targets For 1H 2023

<p>Berong Nickel Corporation surpasses targets, transforming a depleted mine into an eco-friendly haven for tourism and sustainable development. </p>

Berong Nickel Exceeds Mine Rehab Targets For 1H 2023

110
110

How do you feel about this story?

Express Your Reaction
Like
Love
Haha
Wow
Sad
Angry

Berong Nickel Corporation (BNC) on Thursday reported that it has so far rehabilitated 30 hectares of the Berong mine in Quezon, Palawan in the first half of the year.

In a disclosure to the stock exchange, parent company DMCI Holdings Inc. said the rehabilitated area is equivalent to 88 percent of the company’s 34 hectares target for 2023.

“We are fully committed to addressing our impacts on the environment and to our host communities. In our first year, we were able to exceed many of our rehabilitation targets,” BNC president Tulsi Das Reyes said.

“The progress we have made in such a short time is a testament to our team’s hard work and dedication,” he added.

BNC said it has installed 672 coconets for erosion control and soil stabilization, and laid down 1,721 meters of geo-textiles to enhance the ecological stability of the areas under rehabilitation.

To fast-track the final mine rehabilitation of Berong, BNC produced 214,052 seedlings, 152 percent higher than its target of 85,000, and has planted 81,709 or 96 percent of its annual target of 85,000 seedlings.

The Berong mine opened in October 2006 and was fully depleted by December 2021.

To be conducted over a six-year period starting June 2022, the Berong final rehabilitation program covers 109 hectares of surface mine, 209 hectares of silt control structures and 25 hectares of stockpile area.

BNC said after rehabilitation, the disturbed areas could be used for eco-tourism, agro-forestry and inland fish farming by the Department of Environment and Natural Resources, local government units and host communities. (PNA)