NephroPlus Philippines Expands Kidney Health Advocacy Through “Kaagapay Sa Kalusugan Ng Bato” Initiative

NephroPlus Philippines expands “Kaagapay sa Kalusugan ng Bato” to bring kidney health education closer to more Filipino communities.

Rudy Project Philippines Announces Its Biggest End Of Season Sale

Rudy Project Philippines closes the season with its biggest sale, giving customers up to 60% off selected performance gear.

More Than A Facebook Group: How Frances Cabatuando Built The Culture Behind Home Buddies

Frances Cabatuando transformed a small Facebook group into Home Buddies, a trusted community where more than 3.2 million Filipinos share practical home ideas.

New Voith MegaDrive Rubber Wire Drive Roll Improves Traction And Ex-tends Runtimes

Voith has introduced MegaDrive, a next-generation rubber wire drive roll cover designed to deliver lasting traction and reduce maintenance in paper production.

Alternergy, Quezelco 1 Partner To Dispatch Power From Alabat Wind Farm

<p>Renewable energy firm Alternergy joins forces with Quezelco 1 to deliver clean power to the Luzon grid, marking a major milestone in sustainable energy efforts. </p>

Alternergy, Quezelco 1 Partner To Dispatch Power From Alabat Wind Farm

100
100

How do you feel about this story?

Express Your Reaction
Like
Love
Haha
Wow
Sad
Angry

Renewable energy firm Alternergy Holdings Corp. has partnered with Quezon 1 Electric Cooperative Inc. (Quezelco 1) to dispatch clean power from Alternergy’s Alabat wind power.

In a disclosure to the Philippine Stock Exchange Wednesday, Alternergy said it signed the cooperation agreement with Quezelco 1 to facilitate the dispatch from the power farm to the Luzon grid.

Through the deal, the memorandum of agreement (MOA) with the electric cooperative can now be executed.

“Our cooperation with Quezelco 1 is very crucial to ensure that the renewable supply from the Alabat Wind Farm Project will be transported and delivered to the main grid within the timeline we have committed under the Green Energy Auction 2 (GEA 2) Program,” AWPC president Knud Hedeager said.

Under the MOA, Alabat Wind Power Corp. (AWPC) will build and commission a 37-kilometer 69kV transmission line from Alabat Wind Power Farm to the Hongdugua Substation of the National Grid Corporation of the Philippines (NGCP).

Quezelco 1, on the other hand, will build a 10-MVA substation and facilitate in securing the right-of-way for the proposed transmission line for Alternergy.

“Transmission connection is one of the most difficult tasks for any power project. We are pleased to be working hand-in-hand with Quezelco 1,” Hedeager added.

Last October, the Alabat Wind Power Farm got the greenlight from the Quezon Provincial Development Council.

In the same month, Alternergy infused an additional PHP80 million from its initial public offering proceeds to the Alabat wind project.

In a previous statement, Alternergy said construction of its wind farm projects in Alabat and Tanay will begin by the first quarter of 2025, following the specific timeline under the GEA 2.

“We are working at a very tight timeline and are very delighted by the support from Quezelco 1 and earlier from the local government of Quezon and Quezelco 1 to ensure that we achieve this,” Hedeaer said. (PNA)