Tiomico Legacy Comes To Life In LINAHE

LINAHE opened with an enthusiastic crowd at Gateway Gallery, showcasing the Tiomico family's artistic journey. Displaying a medley of styles, the exhibition was a vibrant homage to their shared lineage and legacy.

What’s In The Bag? Influencers Unlock foodpanda’s Most Delicious Deals Yet

When the influencers unwrapped the mysterious packages from foodpanda, their surprise was evident.

4 Ways To Prepare For The Future—Even While Still At School

As graduation approaches, many students find themselves reflecting on their future paths. The journey to discovering goals can begin with small steps.

Setting Yourself Up For Success: 5 Things To Consider When Choosing The Right School

Choosing the right school can shape a student’s academic journey in profound ways.

3rd Phase Of P187-M Access Road In Biliran Nears Completion

Good news! the 187.9 million access road in Naval, Biliran is expected to finish in early January 2021.

3rd Phase Of P187-M Access Road In Biliran Nears Completion

45
45

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The third phase of the construction of the PHP187.9-million access road in Naval, Biliran is nearing completion, the Department of Public Works and Highways (DPWH) reported on Saturday.

David Adongay Jr., DPWH-Biliran chief, said the multi-year project from 2018 to 2022 is funded under the convergence program with the Department of Trade and Industry that would link farm communities in the villages of Caraycaray, Cabungaan, and Libtong to the town center and nearby urban areas.

It covers a total of 5.8 km. road concreting with slope protection, masonry barriers, drainage structures, and rehabilitation of damaged pavement, with its third phase construction covering 1.86 km. of the total length now 73.41 percent complete.

Adongay said the third phase has an allocation of PHP46.7-million and is expected to be finished in early January next year.

“This would provide a safer and faster transport of agricultural products for food and resource-based processing such as palay, abaca, copra, cassava, sweet potato, and ginger, among others,” Adongay said in a statement.

The field office has completed the first two phases in 2018 and 2019, respectively, covering 1.6 km. of the access road. (PNA)