Review: ‘A Real Pain’ Shows The Reality Of Us All

Touching on subjects of grief, vulnerability, family, relationships, and world history, “A Real Pain” shows us the reality that all of us are in pain—it’s either we’re just good at hiding it or we’ve become numb enough not to notice.

ASUS Philippines: First To Launch Intel & AMD’s Latest Chips With Zenbook AI Laptops

ASUS Philippines leads the charge with the launch of the 2025 ASUS Zenbook series, featuring the latest Intel and AMD chips. #ASUS #Zenbook #ThinandLight #AIPC #PAGEONExASUS

Be Your Best Self This Love Month With Ever Bilena

Love yourself this February with Ever Bilena’s budget-friendly beauty picks! From skincare to hair care, it’s time to shine your brightest.

PRSP Honors PAGEONE Group As First Agency Of The Year Hall Of Fame At 60th Anvil Awards

PAGEONE Group makes history as the first and only PR agency to win five AOY awards, earning its place as the only PR agency in the prestigious Hall of Fame category. #PAGEONEGroup #60thAnvilAwards #AnvilAwards #AnvilAwardsHallOfFame

NIA Fast-Tracks Jalaur Dam Project To Boost Yield, Food Security

NIA prioritizes the Jalaur Dam Project to support local farmers and enhance rice production effectively.

NIA Fast-Tracks Jalaur Dam Project To Boost Yield, Food Security

864
864

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

To further boost local palay (unhusked rice) yield and help ensure food security, the National Irrigation Administration (NIA) on Friday vowed to fast-track the completion of the second phase of the Jalaur dam project in Iloilo province.

This is in line with the directives of President Ferdinand R. Marcos Jr. to prioritize food affordability and security for Filipinos.

The PHP19.698 billion Jalaur River Multipurpose Project – Stage II (JRMP-II), the first large-scale reservoir project outside Luzon, covers the construction of a 109-meter-high dam, a 38-meter afterbay dam across the Jalaur River, and a catch dam in Alibunan River in Calinog town.

NIA Administrator Eduardo Guillen told the Philippine News Agency that they can complete the project next year once they have secured the additional budget of PHP3 billion.

“Tapos namin lahat iyan kung i-release nila this year iyong remaining na PHP3 billion. Ideal dapat mga last quarter, until man lang sana October, timing para mapa-bid namin (We can finish it all once they release the remaining PHP3 billion. The ideal [release] would be last quarter, until October, just in time for our bidding),” he said in a phone interview.

“Para (So that) by December or by January, ma-maximize nila iyong (they can maximize the) dry season weather,” he added, referring to around 25,000 farmers who can benefit from the dam project.

He said the additional budget may be sourced from an unprogrammed or contingency fund of the administration, subject to the approval of the National Economic and Development Authority and release of the Department of Budget and Management.

The JRMP-II is expected to increase the production of farmers in Iloilo to an annual yield of around 320,000 metric tons (MT) or 320 million kilograms of palay, equivalent to 160,000 MT per cropping.

“Hindi lang mag-i-increase ng cropping intensity, mag-i-increase pati iyong yield. Kaya malaking bagay ito, makakatulong sa food security natin. Dahil masisiguro natin na mas mataas ang yield ng farmers natin at mailalayo pa sa mga bagyo (We will not only increase the cropping intensity, but the yield as well. That’s why it’s very significant for our food security. Because we can be sure that our farmers will have higher yield and will be even spared from typhoons),” Guillen said.

Saved funds

Guillen, meanwhile, said the NIA saved funds after it turned down the proposed design changes from its Korean contractor, Daewoo Engineering and Construction Co., Ltd.

“Around PHP24 billion pa para matapos. Pero ayaw ko iyon, hindi ako pumayag kasi wala naman magiging additional area na ma-generate iyong ma-irrigate (just to be completed. But I don’t want that. I did not allow it because there’s no additional area for irrigation),” Guillen said.

“Parang gumastos ng additional PHP24 billion pero wala naman additional na pakinabang iyong farmers natin (It seems like you have spent additional PHP24 billion without additional benefit to farmers),” he said, citing the proposed increase in the slope of the high line canal under the JRMP-II.

To date, the NIA has reported a 76.94-percent completion of the construction of three dams and a 16-kilometer-high line canal under the contract with Daewoo.

In total, the target construction of the 80.7-km high line canal will be crucial for annual irrigation, bulk water supply, hydroelectric power and eco-tourism, among others.

The JRMP-II, which commenced in 2012, was funded through a grant from the South Korean government and equity from the Philippine government. (PNA)