How One Man’s Fight For Survival Shaped Asia’s Largest Dialysis Network

Asia’s largest dialysis network began with one man’s fight to survive and grew into a mission shaped by human need.

Cathay Land Taps COREnergy To Boost Energy Efficiency Across Developments

Cathay Land’s partnership with COREnergy highlights how real estate developments can make energy efficiency part of long-term growth.

Nestlé PH Partners With Robinsons Supermarket To Launch Reverse Vending Machines For Sachets

Nestlé Philippines and Robinsons Supermarket turn plastic recovery into a more accessible habit through reverse vending machines for sachets.

Reputation Now Sits At The Leadership Table

Reputation is no longer built by words alone, but through consistent decisions, responsible governance, and leadership behavior over time.

NAIA Inaugurates Improved Runway, Expanded Terminal 2

The Ninoy Aquino International Airport (NAIA) will upgrade its runway and expand its terminal 2 with over PHP900 Million budget.

NAIA Inaugurates Improved Runway, Expanded Terminal 2

408
408

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Manila International Airport Authority (MIAA) inaugurated on Tuesday the improved runway 13/31 at the Ninoy Aquino International Airport (NAIA), as well as the expanded NAIA Terminal 2.

More than PHP400 million was spent for the runway upgrade, while over PHP500 million was allocated for the Terminal 2 expansion.

“It only took more than a year to upgrade the runway. Because of the pandemic, fewer flights, and less people, the work was finished faster,” Media Affairs Division head Jess Martinez told the Philippine News Agency.

Martinez said the overlay and rehabilitation of the runway included putting of cement, as asphalt was previously used for the runway. The additional taxiway was also opened.

A taxiway would save time in terms of aircraft movements per hour because the aircraft would not need to wait or traverse the whole length of the runway, and just take the taxiway to exit, he noted.

All domestic and international flights could use this taxiway, although limited to the Airbus A321 and below types of aircraft, Martinez said.

He also pointed out that runway overlays should be done every three to four years.

With the recent upgrade, the next repair or upgrading maybe after six years, he said.

Meanwhile, an additional 2,800 square meters was used for the expansion of NAIA Terminal 2.

The expansion was mainly for the arrival and conveyor area, lobby, and check-in in the departure area. (PNA)