Review: ‘A Real Pain’ Shows The Reality Of Us All

Touching on subjects of grief, vulnerability, family, relationships, and world history, “A Real Pain” shows us the reality that all of us are in pain—it’s either we’re just good at hiding it or we’ve become numb enough not to notice.

ASUS Philippines: First To Launch Intel & AMD’s Latest Chips With Zenbook AI Laptops

ASUS Philippines leads the charge with the launch of the 2025 ASUS Zenbook series, featuring the latest Intel and AMD chips. #ASUS #Zenbook #ThinandLight #AIPC #PAGEONExASUS

Be Your Best Self This Love Month With Ever Bilena

Love yourself this February with Ever Bilena’s budget-friendly beauty picks! From skincare to hair care, it’s time to shine your brightest.

PRSP Honors PAGEONE Group As First Agency Of The Year Hall Of Fame At 60th Anvil Awards

PAGEONE Group makes history as the first and only PR agency to win five AOY awards, earning its place as the only PR agency in the prestigious Hall of Fame category. #PAGEONEGroup #60thAnvilAwards #AnvilAwards #AnvilAwardsHallOfFame

LRT 2 Extension Completion In 2020 Doable: DMCI

LRT 2 Extension Completion In 2020 Doable: DMCI

15
15

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

Construction firm DM Consunji Inc. (DMCI) said it has started installing the electromechanical system (EMS) for the Light Rail Transit (LRT) Line 2 East extension, which is targeted to be finished by the last quarter of 2020.

DMCI President and Chief Executive Officer Jorge Consunji said: “We are turning over the two stations, Masinag (in Antipolo) and the Emerald (Station).”

“We are starting already the electromechanical (system) of Line 2. Mag install na kami ng (we will install) rails, power, communications,” he said in an interview last week, noting the EMS is also composed of the signaling system.

Consunji cited that the Department of Transportation (DOTr) Secretary Arthur Tugade wants the LRT 2 Extension project to be completed by last quarter next year.

“Tingin namin kaya (We think it is doable),” he added.

The new stations are expected to accommodate an additional 80,000 passengers, boosting the LRT-2’s current daily ridership of 240,000 passengers.

The DOTr last February awarded the PHP3.2-billion contract to the joint venture between Japan-based firm Marubeni Corporation and DMCI for the installation of track works and EMS, which formed Package 3 of the LRT East Extension Project.

Package 1, which involves the construction of a viaduct, was completed in March 2017, while Package 2 involved the construction of Emerald and Masinag stations.

The LRT-2 runs from Santolan in Pasig City to Recto in Manila. (PNA)