More Than A Facebook Group: How Frances Cabatuando Built The Culture Behind Home Buddies

Frances Cabatuando transformed a small Facebook group into Home Buddies, a trusted community where more than 3.2 million Filipinos share practical home ideas.

New Voith MegaDrive Rubber Wire Drive Roll Improves Traction And Ex-tends Runtimes

Voith has introduced MegaDrive, a next-generation rubber wire drive roll cover designed to deliver lasting traction and reduce maintenance in paper production.

The Mayora Who Built A Barangay Before She Had A Blueprint

Frances Cabatuando transformed a simple need for home inspiration into Home Buddies, an online community where millions of Filipinos now share practical advice.

Oman–Philippines 3: Strategic Majlis Opens In Manila To Build On Decades Of Migration Ties Through Trade And Investment

Oman and the Philippines are building on people-to-people connections to strengthen cooperation in investment, commerce, and shared growth.

DOE Exec Sees Normalization Of Luzon Power Supply

DOE Exec Sees Normalization Of Luzon Power Supply

73
73

How do you feel about this story?

Express Your Reaction
Like
Love
Haha
Wow
Sad
Angry

Energy Undersecretary, Felix William Fuentebella has discounted another yellow alert status for the Luzon grid on Wednesday, as maintenance works on the Malampaya gas field in offshore Palawan is expected to end Tuesday.

“We don’t see any yellow alert status for tomorrow because of the additional 1,620 MW (megawatts) from the natural gas plants,” he told journalists in a Viber message Tuesday.

“We expect the completion of Malampaya maintenance today, 15 October 2019. Once gas supply is available, Ilijan Blocks A and B (2 x 600MW) and San Gabriel (420 MW) will be operation starting tomorrow,” he added.

The Malampaya gas field was on maintenance shutdown since October 12, 2019.

Yellow alert was again raised in the Luzon grid on Monday due to large power supply deficiency partly due to the Malampaya maintenance shutdown.

Forced outage for the day affected capacity reaching 1,163 megawatts (MW) based on the total installed capacity of five power plants that include the Sual coal-fired power plant.

Team Energy Corporation’s (TEC) 647 MWs have been on forced outage due to condenser tube leak since last October 11.

Fuentebella said “Sual Unit 1, as per their report yesterday, (said) they are targeting to complete the repair and ‘washing’ of turbine by 21 or 22 October 2019.”

“PMS (preventive maintenance schedule) of Sual Unit 2, which is scheduled to start on 19 October 2019 and end on 17 November 2019, will be moved until Unit 1 is available and stable,” he added. (PNA)