Nestlé Expands CHUCKIE Ready-To-Drink Plant In Tanauan City To Bring More Happy Childhood Memories

Nestlé Philippines has expanded its CHUCKIE ready-to-drink facility in Tanauan City, adding capacity to produce another 144 million packs of chocolate milk annually.

Shaping Digital Lending In PH Through Dignity, Data, And Consumer-Centric Co-Regulation

Tala frames digital lending around dignity, data, and consumer control as the Philippines builds a more inclusive credit ecosystem.

Why Upgrading Your Fuel Is The Smarter Choice

Caltex fuels with Techron technology are designed to help clean harmful engine deposits and support more efficient vehicle performance over time.

NephroPlus Philippines Brings Kidney Health Awareness And Prevention To Indigenous Community In Oriental Mindoro

NephroPlus Philippines continues to complement dialysis care with community-based efforts that encourage prevention, early detection, and greater awareness of kidney health.

DOE Exec Sees Normalization Of Luzon Power Supply

DOE Exec Sees Normalization Of Luzon Power Supply

79
79

How do you feel about this story?

Express Your Reaction
Like
Love
Haha
Wow
Sad
Angry

Energy Undersecretary, Felix William Fuentebella has discounted another yellow alert status for the Luzon grid on Wednesday, as maintenance works on the Malampaya gas field in offshore Palawan is expected to end Tuesday.

“We don’t see any yellow alert status for tomorrow because of the additional 1,620 MW (megawatts) from the natural gas plants,” he told journalists in a Viber message Tuesday.

“We expect the completion of Malampaya maintenance today, 15 October 2019. Once gas supply is available, Ilijan Blocks A and B (2 x 600MW) and San Gabriel (420 MW) will be operation starting tomorrow,” he added.

The Malampaya gas field was on maintenance shutdown since October 12, 2019.

Yellow alert was again raised in the Luzon grid on Monday due to large power supply deficiency partly due to the Malampaya maintenance shutdown.

Forced outage for the day affected capacity reaching 1,163 megawatts (MW) based on the total installed capacity of five power plants that include the Sual coal-fired power plant.

Team Energy Corporation’s (TEC) 647 MWs have been on forced outage due to condenser tube leak since last October 11.

Fuentebella said “Sual Unit 1, as per their report yesterday, (said) they are targeting to complete the repair and ‘washing’ of turbine by 21 or 22 October 2019.”

“PMS (preventive maintenance schedule) of Sual Unit 2, which is scheduled to start on 19 October 2019 and end on 17 November 2019, will be moved until Unit 1 is available and stable,” he added. (PNA)