BISELCO Awards 15-Year Power Supply Deal To CIPC To Strengthen Palawan’s Energy Security

BISELCO has awarded a 15-year power supply deal to CIPC, aimed at enhancing Palawan’s energy security.

Vivant Hits Record PHP2.3 Billion Core Net Income In 2024 Amid Strong Growth

Vivant Corporation reports a remarkable 20% increase in consolidated core net income for 2024, reaching Php 2.3 billion.

ASUS Zenbook A14: The Lightest Zenbook AI Laptop Is In The Philippines

The Zenbook A14 is setting new standards in the world of lightweight laptops with its remarkable design. #PAGEONExASUS

GALLANT: Inspiring Local Champions, Awakening Global Potential

GALLANT is here to inspire local champions and awaken global potential. The time to step up is now.

DOE Exec Sees Normalization Of Luzon Power Supply

DOE Exec Sees Normalization Of Luzon Power Supply

24
24

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

Energy Undersecretary, Felix William Fuentebella has discounted another yellow alert status for the Luzon grid on Wednesday, as maintenance works on the Malampaya gas field in offshore Palawan is expected to end Tuesday.

“We don’t see any yellow alert status for tomorrow because of the additional 1,620 MW (megawatts) from the natural gas plants,” he told journalists in a Viber message Tuesday.

“We expect the completion of Malampaya maintenance today, 15 October 2019. Once gas supply is available, Ilijan Blocks A and B (2 x 600MW) and San Gabriel (420 MW) will be operation starting tomorrow,” he added.

The Malampaya gas field was on maintenance shutdown since October 12, 2019.

Yellow alert was again raised in the Luzon grid on Monday due to large power supply deficiency partly due to the Malampaya maintenance shutdown.

Forced outage for the day affected capacity reaching 1,163 megawatts (MW) based on the total installed capacity of five power plants that include the Sual coal-fired power plant.

Team Energy Corporation’s (TEC) 647 MWs have been on forced outage due to condenser tube leak since last October 11.

Fuentebella said “Sual Unit 1, as per their report yesterday, (said) they are targeting to complete the repair and ‘washing’ of turbine by 21 or 22 October 2019.”

“PMS (preventive maintenance schedule) of Sual Unit 2, which is scheduled to start on 19 October 2019 and end on 17 November 2019, will be moved until Unit 1 is available and stable,” he added. (PNA)