Review: ‘A Real Pain’ Shows The Reality Of Us All

Touching on subjects of grief, vulnerability, family, relationships, and world history, “A Real Pain” shows us the reality that all of us are in pain—it’s either we’re just good at hiding it or we’ve become numb enough not to notice.

ASUS Philippines: First To Launch Intel & AMD’s Latest Chips With Zenbook AI Laptops

ASUS Philippines leads the charge with the launch of the 2025 ASUS Zenbook series, featuring the latest Intel and AMD chips. #ASUS #Zenbook #ThinandLight #AIPC #PAGEONExASUS

Be Your Best Self This Love Month With Ever Bilena

Love yourself this February with Ever Bilena’s budget-friendly beauty picks! From skincare to hair care, it’s time to shine your brightest.

PRSP Honors PAGEONE Group As First Agency Of The Year Hall Of Fame At 60th Anvil Awards

PAGEONE Group makes history as the first and only PR agency to win five AOY awards, earning its place as the only PR agency in the prestigious Hall of Fame category. #PAGEONEGroup #60thAnvilAwards #AnvilAwards #AnvilAwardsHallOfFame

Cavitex-C5 Link Expressway Toll Collection Starts Oct 24

Cavitex-C5 Link Expressway Toll Collection Starts Oct 24

24
24

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

Toll fees will be collected for the first 2.2 kilometers of the Cavitex-C5 Link Expressway starting October 24.

This, after the Toll Regulatory Board approved the collection of a “provisional initial toll”.

Christopher Lizo, Pacific Tollways Company Group Chief Finance Officer and Cavitex Infrastructure Corp (CIC) Chief Operating Officer, said that although there is a proposed toll fee for the whole 7.7-kilometer expressway, the provisional toll fee applies only to the first segment.

“The toll fee is ‘provisional’ because it only applies to one (which means the 2.2- km segment) of the 2 segments,” he said.

CIC will start implementing provisional toll fees of PHP22, PHP44 and PHP66 for Classes 1 (cars), 2 (minivans and buses) and 3 (large truck and trailers) on October 24.

The first 2.2- km segment, which they offered for free for three months, has served a daily vehicle volume of 8,000, Lizo said.
It somehow helped decongest major chokepoints during peak hours along Sales Interchange near Villamor Airbase, South Luzon Expressway (SLEX) and West Service Road, and Epifanio Delos Reyes Avenue (EDSA), Lizo added.

The CIC will continue its work on the second segment, or the next 5.5 kms starting November. Once completed, the entire alignment is seen to serve 50,000 vehicles daily.

The final toll rate will be given once the whole 7.7 -km route is operational in 2021, Lizo said. (PNA)